Dampier Peninsula

Location: 4 x Indigenous Communities
Client: Aurora Environmental
Role: Sub-Contractor
Status: Completed 2021
Project Team: Demolition and Asbestos works team
Project Director: Stephen King
Project Manager:
Site Supervisor: Rex Rua
Site Team: Rex Rua

Detailed Project Description:

Remediate various locations on the Community lands that were impacted from construction waste contaminated with asbestos and removal of domestic waste.. The works involved the following; 

  • Construction of 3 containment cells to hold an estimated 20,000m3 
  • Sort through the stockpiles to remove metal for recycling and clean rocks for reuse onsite
  • Emu pick and remove asbestos impacted soils at various locations across the sites over an area of3ha.
  • Placing all waste materials 20,000M3 into the containment cells and compact in layers
  • Cap the containment cells with geotextile and clean soil capping layer
  • Erect fencing around containment cells
  • Levelling, clearing of site
  • Spreading topsoil across the sites
  • Remove steel offsite

Works were undertaken using the following resources;

  • Excavation and remediation machinery included; 2 x excavators, Rockbreaker, 14t Padfoot roller, Skid Steer, Moxy,  Semi tippers, Front End  Loader and Water Cart.